Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.
NV Energy. Utility; permanent service expected in 2 to 3 years; dedicated on-site substation within the bond-financed project reported
South Valley temporary gas plant. 144 MW temporary natural gas plant to bridge interconnection; PUCN application filed 2026-04-20 reported
Fleet Data Centers (build-to-suit). Greenfield on 252 acres; dual two-story buildings under construction since May 2026; GC not named reported
Not disclosed. Tenant-controlled inferred
Not disclosed. Tenant-controlled inferred