WhiteFiber NC-1

WhiteFiber · Madison, Rockingham County, North Carolina

Verified by Center RegistryChecked against 5 sources, including primary filings and releases
Open on the map →
40 MW
Critical IT planned
35 MW
Energized today
2026
First power
SERC
Grid region · location approximate
In brief

What makes it notable.

  1. A retrofit of a roughly 1 million square foot former textile plant on 96 acres, bought for $45M, to Tier 3-equivalent specs: up to 150 kW per cabinet, N+1 cooling and a target PUE of 1.3.
  2. Duke Energy Carolinas staged power at 24 MW, 40 MW and 99 MW within four years, with work done to deliver the initial 54 MW gross as of May 2026.
  3. Feasibility is about 200 MW, with a company target near 300 MW gross over time. About 35 MW of the 40 MW contracted was operating by November 2026, after switchgear commissioning issues interrupted service.
Deal anatomy

Six layers, and who holds each.

Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.

Power
Duke Energy Carolinas
Site and build
Enovum Data Centers (WhiteFiber subsidiary)
Compute
Not disclosed
Cloud operator
Not disclosed
Anchor tenant
Members
Capital
Members
Free for professionals in AI infrastructure.
Timeline

From here to full build.

  1. Nov 2026Today
  2. 2026First powerabout 35 of 40 MW operational by Nov 2026, after switchgear commissioning issues
  3. ~2029Full buildout99 MW within 4 years of the May 2025 Duke letter agreement
The detail

Each party's role.

Power

Duke Energy Carolinas. Utility; 99 MW letter agreement filed as an SEC exhibit (24 MW ~Sep 2025, 40 MW ~Apr 2026, 99 MW within 4 years); work completed to deliver the initial 54 MW gross as of May 2026; feasibility ~200 MW, company targets ~300 MW gross over time

Site and build

Enovum Data Centers (WhiteFiber subsidiary). In-house developer retrofitting the ~1M sq ft former Unifi textile plant (96 acres, bought $45M) to Tier 3-equivalent, up to 150 kW/cabinet, N+1 cooling, target PUE 1.3

Compute

Not disclosed. Tenant (Nscale) deploys its own GPU systems inferred

Cloud operator

Not disclosed. Tenant-controlled inferred

Related sites

Nearby in the buildout.

Sources

The record behind this page.

Center Registry

Who keeps this record.

Center Registry tracks the US AI data center buildout site by site. Every record is checked against primary sources: SEC filings, company releases, utility and grid operator records. A record changes when a filing changes it.

Need capacity in North Carolina?

Looking for GPU colocation or a campus in North Carolina? Tell us the megawatts and the date, and a reply comes back within one business day. Hold a powered site there yourself? Tell us about it.

Tell us what you need →