Stargate Abilene

Crusoe · Abilene, Taylor County, Texas

Verified by Center RegistryChecked against 2 sources, including primary filings and releases
Open on the map →
1,200 MW
Gross planned
200 MW
Energized today
2025-09
First power
ERCOT
Grid region · location approximate
In brief

What makes it notable.

  1. Power comes from Lancium's Clean Campus with on-site gas generation, a behind-the-meter arrangement, and Crusoe is the design-build EPC with direct-to-chip liquid cooling.
  2. 200 MW is live now against 1.2 GW planned gross, with first power in September 2025 and full buildout targeted for the fourth quarter of 2026.
  3. The compute is NVIDIA GB200, at a stated scale of roughly one million H100-equivalents.
Deal anatomy

Six layers, and who holds each.

Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.

Power
Lancium Clean Campus + on-site gas
Site and build
Crusoe (design-build)
Compute
NVIDIA GB200
Cloud operator
Crusoe + Oracle Cloud
Anchor tenant
Members
Capital
Members
Free for professionals in AI infrastructure.
Timeline

From here to full build.

  1. 2025-09First power
  2. Nov 2026Today
  3. 2026-Q4Full buildout
The detail

Each party's role.

Power

Lancium Clean Campus + on-site gas. Powered land, behind-the-meter generation reported

Site and build

Crusoe (design-build). EPC, direct-to-chip liquid cooling reported

Compute

NVIDIA GB200. GPU fabric, ~1M H100-equivalents at buildout

Cloud operator

Crusoe + Oracle Cloud. Neocloud operator

Related sites

Nearby in the buildout.

All AI data centers in Texas →

Sources

The record behind this page.

Center Registry

Who keeps this record.

Center Registry tracks the US AI data center buildout site by site. Every record is checked against primary sources: SEC filings, company releases, utility and grid operator records. A record changes when a filing changes it.