20 MW
Critical IT planned
20 MW
Energized today
2024-Q2
First power
ERCOT
Grid region · location approximate
Deal anatomy

Six layers, and who holds each.

Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.

Power
Austin Energy
Site and build
Core Scientific (in-house)
Compute
NVIDIA
Cloud operator
CoreWeave
Anchor tenant
Members
Capital
Members
Free for professionals in AI infrastructure.
Timeline

From here to full build.

  1. 2024-Q2First powerCoreWeave lease operations commenced
  2. Nov 2026Today
  3. 2026Full buildout~20 MW leased and billing as of 2026-11-05
The detail

Each party's role.

Power

Austin Energy. Municipal utility, 20 MW of gross utility capacity at the Austin facility (FY2025 10-K utility table)

Site and build

Core Scientific (in-house). Leased tier 3 data center formerly occupied by Hewlett Packard, fitted out for high-density HPC colocation; lease operations began Q2 2024 reported

Compute

NVIDIA. CoreWeave GPU fleet hosted at the site (models not disclosed) reported

Cloud operator

CoreWeave. AI cloud platform running on the hosted GPUs reported

Related sites

Nearby in the buildout.

All AI data centers in Texas →

Sources

The record behind this page.

Center Registry

Who keeps this record.

Center Registry tracks the US AI data center buildout site by site. Every record is checked against primary sources: SEC filings, company releases, utility and grid operator records. A record changes when a filing changes it.